Update 5/13/15

posted May 13, 2015, 11:14 AM by Robert Wilson
Here is an updated timeline of the move to interim housing for staff.

May 15 – Interim Housing contractor begins work
May 27 – June 12, Interim Housing units delivered
June 18 – June 28, 10 days to move EVERYTHING out of building
June 29 – Demolition of main building begins
August 1 – Interim Housing for Administration, Guidance Services and Support Staff complete
August 14 – Interim Housing for classrooms complete